A2SEA installs first turbine on Dudgeon Offshore Wind Farm

10.01.2017
Sea Challenger and her crew, together with Statoil and Siemens installed the first turbine on Dudgeon OWF. (Photo: Statoil, Byron Price / Rix Leopard)
Sea Challenger and her crew, together with Statoil and Siemens installed the first turbine on Dudgeon OWF. (Photo: Statoil, Byron Price / Rix Leopard)

A2SEA’s Sea Challenger installed the first out of the 67 Siemens 6 MW turbines on the 402 MW Dudgeon Offshore Wind Farm for Statoil, Masdar and Statkraft. For the next months, the vessel will install the turbines being shipped from Green Port Hull in the UK. This is the first time, the Port of Hull will be used as load out port for an offshore wind project.

Since September 2016, Sea Challenger has been used for offshore accommodation during completion and commissioning of the offshore substation. The vessel was jacked up to 20 m above sea level and had accommodation for 80 persons including the A2SEA crew.

Jens Frederik Hansen CEO at A2SEA, said: ”We have wide experience in handling the Siemens 6 MW turbines, but it cannot be done without good team work. It is a great pleasure to once again work together with Siemens, but also our renewed cooperation and partnership with Statoil, which started on their first offshore wind project Sheringham Shoal, and now continues on the Dudgeon

project.”

The Dudgeon Offshore Wind Farm is owned by Statoil (35%), Masdar (35%) and Statkraft (30%) and is situated 32 km off the coast of the seaside town of Cromer in North Norfolk in the UK. When fully commissioned by 2017, the Dudgeon Offshore Wind Farm will provide well over 400,000 households with renewable power.

Silke Funke / A2 SEA

Similar Entries

With the installation of the last of a total of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)

The offshore wind power plant Sandbank, located 90 kilometres west of the island of Sylt, is now fully installed and commissioned. On 21 January the installation vessel MPI Adventure together with Siemens erected the last turbine. Four days after that the last turbine “SB41” has achieved ‘final commissioning’ already.

42 Siemens SWT-7.0-154 units will supply clean energy at Rentel offshore project for approximately 300,000 Belgian households. (Photo: Siemens Wind Power)

Siemens has entered the offshore wind market in Belgium with a first order of direct drive wind turbines for the 309 MW Rentel wind project.

EnBW Energie Baden-Württemberg AG has increased the pace at which it is expanding wind energy at sea: Just a few days after having its bid for the 900 megawatt project EnBW He Dreiht accepted in Germany's first offshore wind power auction, the company's Supervisory Board has now given the green light for the next offshore wind farm EnBW Albatros and approved the final decisions taken regarding construction and investment.

The first wind energy plant of the offshore wind farm Nordergründe has been installed. (Photo: wpd)

On August 16, the first wind energy turbine has been installed at the offshore wind site Nordergründe in the German North Sea. The first turbine of the 111 MW wind park was produced by Senvion and has a capacity of 6.15 MW.