First turbine successfully installed at Nordsee One

09.03.2017
 Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)

Installation of the 54 Senvion 6 MW wind turbines that will comprise the Nordsee One Offshore Wind Farm has commenced at the base port in Eemshaven.

Two sets of wind turbines each consisting of a fully assembly steel tower, a nacelle and a pre-assembled rotor, were loaded onto the installation vessel MPI Enterprise, which transported the components to the construction site at sea located approximately 40 km north off the island of Juist. Upon arrival at the offshore site, the first of the two turbines was installed using the installation vessel’s own crane.

The nacelles alone weigh-in at approx. 335 tonnes, the tower itself measures almost 70 metres overall in length, and weighs over 240 tonnes. Each rotor blade is 61 meters in length and weighs approximately 20 tonnes.

In April 2016 installation of the turbine foundations was completed. The substation was installed last summer, and the inter-array cable laying was successfully completed in September 2016. Once completed, the Nordsee One wind farm will consist of 54 wind turbines of the type Senvion 6.2M126 with an overall installed capacity of 332 MW. Commissioning of the wind farm is anticipated by the end of 2017. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

Pierre Lestienne, Managing Director (CFO) of Nordsee One GmbH explained: “We have reached this important milestone according to schedule and within budget. I'm really proud of this achievement. This outcome is the result of precise planning and efficient execution.”

Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH added: “The team worked together hand-in-hand, so the loading of the first major components at our base port in Eemshaven, as well as the installation at sea, both went very smoothly. We look forward to installation of the next turbines, which will follow immediately. We plan to have all turbines installed and commissioned by the end of this year.”

Northland Power / innogy SE / 
Nordsee One GmbH / Silke Funke

Similar Entries

Zentech and Renewables Resources International announced to build the first Jones Act compliant U.S. installation vessel. "This vessel will provide the now evolving U.S. Offshore Wind Industry with a much needed and cost competitive marine logistic solution,” stated Zentech in a press release. The U.S. Jones Act requires for all vessels that are transporting goods to and from U.S. ports, such as components for an offshore wind farm, to be U.S. built and operated. Zentech Incorporated is a marine engineering and naval architecture firm specializing in the offshore oil and gas and renewable energy industries.

The prototype of Gamesa’s new turbine G132-3.3 MW is now installed. (Photo: Gamesa)

Gamesa has announced the installation of the prototypes of its newest turbine models G126-2.5 MW and G132-3.3 MW at the Alaiz R&D facility in Navarra, Spain.

With the installation of the last of a total of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)

The offshore wind power plant Sandbank, located 90 kilometres west of the island of Sylt, is now fully installed and commissioned. On 21 January the installation vessel MPI Adventure together with Siemens erected the last turbine. Four days after that the last turbine “SB41” has achieved ‘final commissioning’ already.

The last rotor of Ararat Wind Farm’s 75 turbines has been installed by contractor Mammoet. The cable trenching and installation by RJE Global is also complete. To finish the project there just remains the connection of cables to the turbines required to transport electricity generated to the substation and into the grid, commissioning of the remaining turbines and site rehabilitation.