First turbine successfully installed at Nordsee One

09.03.2017
 Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)

Installation of the 54 Senvion 6 MW wind turbines that will comprise the Nordsee One Offshore Wind Farm has commenced at the base port in Eemshaven.

Two sets of wind turbines each consisting of a fully assembly steel tower, a nacelle and a pre-assembled rotor, were loaded onto the installation vessel MPI Enterprise, which transported the components to the construction site at sea located approximately 40 km north off the island of Juist. Upon arrival at the offshore site, the first of the two turbines was installed using the installation vessel’s own crane.

The nacelles alone weigh-in at approx. 335 tonnes, the tower itself measures almost 70 metres overall in length, and weighs over 240 tonnes. Each rotor blade is 61 meters in length and weighs approximately 20 tonnes.

In April 2016 installation of the turbine foundations was completed. The substation was installed last summer, and the inter-array cable laying was successfully completed in September 2016. Once completed, the Nordsee One wind farm will consist of 54 wind turbines of the type Senvion 6.2M126 with an overall installed capacity of 332 MW. Commissioning of the wind farm is anticipated by the end of 2017. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

Pierre Lestienne, Managing Director (CFO) of Nordsee One GmbH explained: “We have reached this important milestone according to schedule and within budget. I'm really proud of this achievement. This outcome is the result of precise planning and efficient execution.”

Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH added: “The team worked together hand-in-hand, so the loading of the first major components at our base port in Eemshaven, as well as the installation at sea, both went very smoothly. We look forward to installation of the next turbines, which will follow immediately. We plan to have all turbines installed and commissioned by the end of this year.”

Northland Power / innogy SE / 
Nordsee One GmbH / Silke Funke

Similar Entries

Luxembourg special fund FP Lux Investments is further expanding its wind power portfolio. With the purchase of the Ratiperä wind farm in southwestern Finland, the portfolio of the Wind Infrastructure I sub-fund has grown to 19 wind farms with 94 turbines and an installed capacity of 269 MW. Of this, a volume of 194 MW was acquired in Germany, 31 MW in France and 44 MW in Finland. The deal was advised by the internationally active M&A advisors and asset manager re:cap global investors ag, which manages the entire evaluation and acquisition process of the special fund.

Innogy Renewables UK Ltd. is pleased to announce that all 28 turbines at Brechfa Forest West Wind Farm are now operational and exporting renewable energy to the National Grid. With an installed capacity of 57.4MW, Brechfa Forest West can generate enough renewable energy to meet the equivalent energy needs of approximately 38,800 average UK homes; that is almost half of all the households in Carmarthenshire.

Slowly but surely the floating offshore wind energy sector is becoming more and more important, particularly because of the fact that the number of locations with shallow waters suitable for fixed-bottom foundations is limited. Floating wind is turning into a highly scalable future energy source because the wind resource in deep waters is extensive and offers a significant potential for marine renewable energy development and growth to many countries.

The Wind Turbine Market is set to grow from its current market value of more than $50 billion to over $70 billion by 2024; as reported in the latest study by Global Market Insights, Inc.