Offshore wind project Rampion starts power generation

28.11.2017
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)

The offshore wind farm Rampion in the English Channel has started generating electricity. According to E.ON, the first turbine was commissioned. 115 additional turbines will be connected to the grid in stages over the next few months.

The offshore work for the Rampion project began in autumn 2015 with the preparation of the seabed for the turbine foundations. The first monopile was installed at the beginning of 2016. The installation of the turbines began in March 2017 and was completed ahead of schedule in September.

The 400 MW Rampion project is located 13 kilometres off the Sussex coast. Owners are E.ON, the British Green Investment Rampion Ltd. and the Canadian energy company Enbridge. The project is being built and operated by E.ON as majority owner.

E.ON / Silke Funke

Similar Entries

Sea Challenger and her crew, together with Statoil and Siemens installed the first turbine on Dudgeon OWF. (Photo: Statoil, Byron Price / Rix Leopard)

A2SEA’s Sea Challenger installed the first out of the 67 Siemens 6 MW turbines on the 402 MW Dudgeon Offshore Wind Farm for Statoil, Masdar and Statkraft. For the next months, the vessel will install the turbines being shipped from Green Port Hull in the UK. This is the first time, the Port of Hull will be used as load out port for an offshore wind project.

42 Siemens SWT-7.0-154 units will supply clean energy at Rentel offshore project for approximately 300,000 Belgian households. (Photo: Siemens Wind Power)

Siemens has entered the offshore wind market in Belgium with a first order of direct drive wind turbines for the 309 MW Rentel wind project.

With the installation of the last of a total of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)

The offshore wind power plant Sandbank, located 90 kilometres west of the island of Sylt, is now fully installed and commissioned. On 21 January the installation vessel MPI Adventure together with Siemens erected the last turbine. Four days after that the last turbine “SB41” has achieved ‘final commissioning’ already.

International marine and engineering consultancy LOC Renewables is carrying out marine warranty surveying (MWS) services on what will be the world’s biggest wind farm, DONG Energy’s Hornsea Project One. The site, which will consist of 174 turbines installed off the Yorkshire coast in the North Sea and deliver power to more than one million homes, is scheduled for commissioning in 2020.